The European Commission has presented the REPowerEU plan: its response to the hardship and disruption of the global energy market caused by Russia’s invasion of Ukraine.

Transforming Europe’s energy system is urgent for two reasons: ending the EU’s dependence on Russian fossil fuels and tackling the climate crisis.

The measures of the REPowerEU plan aim to achieve this goal through

  • energy saving
  • the diversification of energy supplies
  • the accelerated roll-out of renewable energy to replace fossil fuels in homes, industry and power generation.

With this recommendation, the Commission addresses – among other topics – precisely the long-standing issue of the excessive length and complexity of authorisation procedures for renewable energy projects.

The current slowness and fragmentation of authorisation procedures are in fact identified as the main obstacles not only to the deployment of such plants as such, but also because they lead to plants that are less efficient than the dynamic innovation achieved in the meantime would allow.

On this basis, the Commission therefore specifies that Member States should:

  • set clearly defined and short deadlines for all the steps needed to authorise the construction and operation of such infrastructure – as well as its connection to the grid – (whose duration should in any case be limited to a maximum of three months);
  • allow applicants to update the technological specifications of their projects in the period between the application and the granting of the authorisation.

Also very important is point 13, which provides that Member States should introduce rules whereby the absence of a response from the competent authorities – within mandatory deadlines – de facto results in the granting of the authorisation (see in this respect the very recent Decree-Law 50/2022, art. 7, paragraph 2).

Again with a view to promoting the deployment of RES (Renewable Energy Sources) plants, the recommendation then asks Member States to quickly identify the onshore and offshore areas suitable for this type of plant (renewables go-to areas), giving priority to degraded areas that cannot be used for agriculture and, at the same time, keeping so-called “exclusion zones” to a minimum, which should in turn be the subject of clear, transparent and reasoned information.

To this end, the Commission invites Member States to make use of the data and information on environmentally sensitive areas available in the digital mapping tool for energy and industry geographical data (Energy and Industry Geography Lab).

Given the innovative impact of the provisions set out in the recommendation, each Member State is required to monitor the implementation of the measures to speed up procedures, reporting to the Commission every two years (starting from March 2023) on the progress made, in order to make authorisation processes more efficient and, consequently, increase the deployment of renewable energy plants.