The closure of the first procedure, with the application deadline on 27 October, does not mark the end of incentives under the NRRP Agrisolar Park call, the measure that supports photovoltaics on the buildings of farming businesses. There will be further reopening windows for the call, spread over the next two to three years. The goal is in fact to allocate each year around 30% of the NRRP resources.

The GSE has not yet published the figures on participation in the first window, but unofficial numbers released by Confagricoltura indicate that applications were submitted for about 35% of the available resources.

As is well known, the total funds available amount to 1.5 billion euros, to develop at least 375 MW of new PV plants, according to the target set in the call, with at least 40% of the funds allocated to projects in Southern Italy.

The timing of the next procedures, as well as any adjustments to the rules, will be decided together with the Ministry of Agricultural, Food and Forestry Policies (Mipaaf).

These will be joined by the new incentives for ground-mounted agrivoltaics; the Ministry of the Environment and Energy Security is finalising the decree in line with the NRRP target of having contracts awarded by December 2024.

The beneficiaries of the Agrisolar Park call are companies active both in primary agricultural production and in the processing of agricultural products.

The former will receive the bulk of the funding, i.e. 1.2 billion euros out of the total 1.5 billion, while processing companies will receive a total of 300 million.

To be eligible for incentives, a photovoltaic system must be newly built with a total capacity between 6 and 500 kWp, and its solar production capacity must not exceed the farm’s combined average annual consumption of thermal and electrical energy, including household consumption.

The maximum eligible expenditure cannot exceed 750,000 euros, although a single beneficiary may apply for the grant for several projects, provided that the total expenditure for the same applicant does not exceed 1 million euros.

Together with the construction of the photovoltaic system, one or more complementary works may be carried out to upgrade the building and energy performance of the roof on which the system is installed (asbestos removal, thermal insulation, ventilated roofing).

The maximum incentive rate is 50% of eligible costs for works in the disadvantaged regions of Southern Italy and 40% of eligible costs for the other regions.

For companies in primary production, the non-repayable grant rate can be increased by 20 percentage points if the beneficiary is a young farmer or a farmer who has set up in the five years prior to the date of the aid application, or if the area concerned is listed among the areas facing significant natural constraints.

In addition, for works in companies processing agricultural products into non-agricultural products, regardless of the region, the maximum incentive rate is instead 30% of eligible costs.

Here too, however, the grant can be increased by 20 percentage points for small enterprises, by 10 percentage points for medium-sized enterprises and by 15 percentage points for investments made in assisted areas.

PHOTOVOLTAICS ON THE RISE: +12% installed plants in the first months of 2022

In the first nine months of 2022, the Italian photovoltaic sector recorded higher values than in previous years. Lazio, Apulia and Lombardy were the best-performing regions.

According to the latest GSE statistics, as of 30 September there were around 1,140,000 photovoltaic plants in operation (+12% compared with the end of 2021), with a total capacity of over 24.2 GW (+7%). Recorded production, just under 24 TWh, increased by around 12% compared with the same period of the previous year.

About half of the plants installed in Italy belong to the industrial sector (including energy-producing companies), which accounts for 51% of total installed capacity; followed by the services (20%), residential (18%) and agricultural (11%) sectors.

35% of plant capacity is ground-mounted, while the remaining 65% is not (on buildings, roofs, canopies, etc.); the total area occupied by ground-mounted plants can be estimated at around 15,800 hectares.

At regional level, Lazio, Apulia and Lombardy are the regions that have installed the most plants. Despite the lead of the Lazio region and the province of Rome, if we take plant yield as the indicator, Lecce is the province with the best performance in 2022, with just under 1,100 operating hours.

(source: GSE)